Vcehome > Oracle > Supply Chain Management (SCM) > 1Z0-1075-20 > 1Z0-1075-20 Online Practice Questions and Answers

1Z0-1075-20 Online Practice Questions and Answers

Questions 4

A plant runs 24x7 daily using three continuous shifts of 8 hours each. One unit of an equipment resource R1 is assigned to each of the three shifts. On a specific work order, the resource R1 is required to work for 2 hours. The resource is set up with an efficiency of 50% and utilization of 100%. R1 is scheduled to start on the given work order at noon. What time will R1 be scheduled to finish, assuming no calendar exceptions have been set?

A. 8:00 PM

B. 12:30 PM

C. 2:00 PM

D. 4:00 PM

E. 1:00 PM

Browse 66 Q&As
Questions 5

The Manufacturing plant has two 8-hour shifts for the work center WC1: Day Shift and Night Shift. You associate four units each for resources R1, R2, R3, and R4 to the work center WC1. The customer wants to assign all units of resource R2 available for Day and Night Shift. Identify the correct sequence of steps to achieve this requirement.

A. Associate Resource R2 with Work Center WC1> Select Available 24 Hours check box> Resource Availability region> Enter 4 in Day Shift Column> Enter 4 in Night Shift Column.

B. Associate Resource R2 with Work Center WC1> Deselect the Available 24 Hours check box> Resource Availability region> Enter 2 in Day Shift Column> Enter 2 in Night Shift Column

C. Associate Resource R2 with Work Center WC1> Select the Available 24 Hours check box> Resource Availability region> Enter 2 in Day Shift Column > Enter 2 in Night Shift Column.

D. Associate Resource R2 with Work Center WC1> Deselect the Available 24 Hours check box> Resource Availability region> Enter 4 in Day Shift Column> Enter 4 in Night Shift Column.

Browse 66 Q&As
Questions 6

A plant operates three continuous daily shifts of eight hours each for five days in a week. One unit of the resource R1 within the plant is assigned for two shifts to work area W1. On a particular day in a given week, due to unscheduled maintenance that needed to be performed on the resource R1, it was not available for two hours during each of the assigned shifts. Determine the available capacity of the resource R1 for that week.

A. 78 hours

B. 76 hours

C. 60 hours

D. 70 hours

Browse 66 Q&As
Questions 7

Identify four parameters that are considered in the calculation of manufacturing lead time in Oracle Manufacturing Cloud.

A. Resource calendars of the work centers involved

B. The primary work definition of the item

C. The lot size of the item

D. The shifts are defined in the plant calendar

E. Plant calendar exceptions

F. Resource calendar exceptions

Browse 66 Q&As
Questions 8

Your Customer has implemented Oracle Cloud Manufacturing and the Manufacturing user is in the

process of defining Work Definition and Operations. However, this user is unable to assign an ad hoc item,

Grease, to an operation.

Identify the reason.

A. The user doesn't have Override Item Structure Components in the Work Definition privileges.

B. An item cannot be assigned on an ad hoc basis.

C. The user doesn't have access to the PIM module.

D. The user doesn't have Data access to create item structure.

Browse 66 Q&As
Questions 9

Your customer runs two daily shifts in her plant: Morning Shift and Evening Shift. A resource LATHE is assigned to the work center W1. There are five units of LATHE available, of which three units are available for the Morning Shift and the remaining units are available for the Evening Shits. Which two actions must you perform to associate LATHE with W1?

A. Do not select the Available 24 Hours check box and in the Resource Availability region, enter 3 against the resource LATHE in the Morning Shift column.

B. Select the Available 24 Hours check box and in the Resource Availability region, enter 3 against the resource LATHE in the Morning Shift column.

C. Select the Available 24 Hours check box and in the Resource Availability region, enter 2 against the resource LATHE in the Evening Shift column.

D. Do not select the Available 24 Hours check box and in the Resource Availability region, enter 2 against the resource LATHE in the Evening Shift column.

E. Do not select the Available 24 Hours check box and in the Resource Availability region, enter 60% against the resource LATHE in the Morning Shift column.

F. Do not select the Available 24 Hours check box and in the Resource Availability region, enter 40% against the resource LATHE in the Evening Shift column.

Browse 66 Q&As
Questions 10

A Production Operator needs to load Work Order Transactions from an external system into Manufacturing

Cloud.

Identify the correct sequence of tasks to be performed.

A. Load Data to Fusion repository> Export File to UCM server > Process Import Operations Transactions> Load file from UCM to Interface table.

B. Export File to UCM server> Load Data to Fusion repository> Process Import Operations Transactions> Load file from UCM to Interface table.

C. Load Data to Fusion repository> Export File to UCM server > Load file from UCM to Interface table >Process Import Operations Transactions.

D. Load Data to Fusion repository> Load File from UCM to Interface table> Export File to UCM server> Process Import Operations Transactions.

Browse 66 Q&As
Questions 11

You have been asked to set up cost estimates for 10 different purchased items. Which two steps could be used to accomplish this task?

A. Use the Mass Edit functionality.

B. Run the ESS process "Update Item Cost Estimate".

C. Enter cost estimates directly into UI.

D. Call web service.

E. Import spreadsheet.

Browse 66 Q&As
Questions 12

In a Manufacturing Cloud post production support environment, a user wants to update some of the

operations in the work orders by using the Midpoint Scheduling feature. However, the user is unable to

update any of the orders.

Identify two reasons.

A. The work order operations do not have operations start or completion date.

B. The scheduled resources are not part of the organization selected by the user.

C. None of the operations include scheduled resources.

D. The operations are missing sequence.

Browse 66 Q&As
Questions 13

The production user wants to report Work Order completion. Identify two ways of reporting the progress of work order at work order operation level.

A. Change Move status to Ready.

B. Complete using quantity completion

C. Complete with Details

D. Quick Complete

E. Change status of Operation to completed

Browse 66 Q&As
Exam Code: 1Z0-1075-20
Exam Name: Oracle Manufacturing Cloud 2020 Implementation Essentials