Organizational theory is a tool used in which Project Human Resource Management process?

A. Manage Project Team

B. Acquire Project Team

C. Develop Project Team

D. Plan Human Resource Management

Browse 704 Q&As
Questions 5

The process of confirming human resource availability and obtaining the team necessary to complete project activities is known as:

A. Plan Human Resource Management.

B. Acquire Project Team.

C. Manage Project Team.

D. Develop Project Team.

Browse 704 Q&As
Questions 6

Retreating from an actual or potential conflict or postponing the issue to be better prepared or to be resolved by others describes which of the five general techniques for managing conflict?

A. Smooth/accommodate

B. Withdraw/avoid

C. Compromise/reconcile

D. Force/direct

Browse 704 Q&As
Questions 7

The process of obtaining seller responses, selecting a seller, and awarding a contract is called:

A. Close Procurements.

B. Control Procurements.

C. Plan Procurements.

D. Conduct Procurements.

Browse 704 Q&As
Questions 8

Sharing good practices introduced or implemented in similar projects in the organization and/or industry is an example of:

A. quality audits

B. process analysis

C. statistical sampling

D. benchmarking

Browse 704 Q&As
Questions 9

What is the name of a graphic display of project team members and their reporting relationships?

A. Role dependencies chart

B. Reporting flow diagram

C. Project organization chart

D. Project team structure diagram

Browse 704 Q&As
Questions 10

The CPI is .92, and the EV is US$172,500. What is the actual cost of the project?

A. US$158,700

B. US$172,500

C. US$187,500

D. US$245,600

Browse 704 Q&As
Questions 11

A purchase order for a specified item to be delivered by a specified date for a specified price is the simplest form of what type of contract?

A. Cost-reimbursable

B. Time and material

C. Fixed price or lump-sum

D. Cost-plus-fixed-fee

Browse 704 Q&As
Questions 12

In a weak matrix, the project manager's role is:

A. part-time

B. full-time

C. occasional

D. unlimited

Browse 704 Q&As
Questions 13

Which of the following is a strategy to deal with positive risks or opportunities?

A. Mitigate

B. Transfer

C. Exploit

D. Avoid

Browse 704 Q&As