When a Belt Poka-Yoke's a defect out of the process entirely then she should track the activity with a robust SPC system on the characteristic of interest in the defect as an early warning system.
A. True
B. False
The Control Limits width varies if the sample size varies for which type of chart?
A. P Charts
B. NP Charts
C. Xbar-R Charts
D. Time Series Charts
After reviewing the Capability Analysis shown here select the statement that is untrue.
A. The process is properly assumed to be a Normal process
B. The Mean of the process moving range is 1.78
C. The process is out of Control
D. This Capability Analysis used subgroups
The design and code review effort is high (process is effective) in a project, and it results in less number of defects injected in UAT phase. Identify the appropriate type of correlation between review effort and number of defects. (Assume that "r" value is good).
A. Positive Correlation
B. Strong Negative Correlation
C. Non linear Correlation
D. Strong Positive Correlation
What is the Probability value of the area under the curve between -1.0 and -2.0 Standard deviation units in Normal Distribution?
A. 0.3413
B. 0.4772
C. 0.1359
D. 0.8185
All the steps given below are phases in DMAIC except:
A. Measure
B. Continue
C. Define
D. Analyze
80% of effects come from 20% of the possible causes. These 20% are called the:
A. Variations in the process
B. Vital Few
C. Cost to the process
D. Waste
Which of these defects per million opportunity (DPMO) levels approximate to four Sigma quality?
A. 308357
B. 66807
C. 6210
D. 233
Process mapping is:
A. a onetime event
B. a tool used for statistical validation
C. a tool used at the end of the DMAIC process
D. an ongoing living document used throughout the DMAIC process
Profit and market share would be the concern of which of the following?
A. Voice of the Customer
B. Voice of the Government
C. Voice of the Process
D. Voice of the Business