Where can you define the valid receivers for production order costs?

A. In the valuation variant

B. In the production scheduling profile

C. In the settlement profile

D. In the costing variant

Browse 80 Q&As
Questions 5

What sequence do you follow in master data maintenance to define the production of a material?

A. Create BOM -> Create work centers -> Create routing -> Carry out component assignment in BOM or routing

B. Create BOM -> Create work centers -> Create routing -> Carry out component assignment in work center

C. Create routing -> Create work centers -> Create BOM -> Carry out component assignment in BOM or routing

D. Create work centers -> Create routing -> Create BOM -> Carry out component assignment in work center

Browse 80 Q&As
Questions 6

You want to use the different options for planning in SAP ECC.

What is the correct sequence of the planning procedures?

A. Sales and operations planning -> Demand management -> Long-term planning -> Material requirements planning -> Capacity planning

B. Material requirements planning -> Demand management -> Sales and operations planning -> Long-term planning -> Capacity planning

C. Long-term planning -> Sales and operations planning -> Demand management -> Material requirements planning -> Capacity planning

D. Demand management -> Sales and operations planning -> Capacity planning -> Long-term planning -> Material requirements planning

Browse 80 Q&As
Questions 7

Which of the following properties applies to multi-site planning in SAP ECC?

A. Multi-site planning can be activated using the corresponding planning strategy.

B. Both withdrawal from alternative plant and stock transfer from another plant are defined via special procurement keys.

C. The use of "scope of planning" (cross-plant total planning) is mandatory for multi-site planning.

D. When using one-step stock transfer posting, transfer stock is created in the receiving plant.

Browse 80 Q&As
Questions 8

Which of the following functions are available in SAP ECC when using capacity leveling? (Choose three)

A. Finite capacity scheduling

B. Setup time reduction

C. Midpoint scheduling

D. Lot size optimization

E. Batch size optimization

Browse 80 Q&As
Questions 9

You use a planning time fence and fixing type 1. You receive a customer order with a material availability date within the planning time fence.

What do you have to consider in this scenario?

A. Planned orders that are created by requirements planning are shifted to the end of the planning time fence.

B. Requirements planning considers only changes that are relevant for scheduling within the planning time fence.

C. The MRP controller cannot create planned orders within the planning time fence.

D. Planned orders are created within the planning time fence and automatically firmed by requirements planning.

Browse 80 Q&As
Questions 10

In which of the following objects can you activate backflushing for production orders? (Choose three)

A. Production scheduling profile

B. Material master (finished product)

C. Material master (component)

D. Routing

E. Work center

Browse 80 Q&As
Questions 11

Which of the following activities within the KANBAN procedure normally triggers subsequent stock posting of the goods receipt?

A. Set "Container in transport"

B. Set "Container empty"

C. Set "Container full"

D. Set "Container in process"

Browse 80 Q&As
Questions 12

You want to plan a finished material using material requirements planning in an SAP ECC system. The resulting planned orders should be scheduled using basic date scheduling (not lead-time scheduling).

Which of the following statements is true for the resulting dependent requirements?

A. When a customer order is created for the finished material, the dependent requirements are automatically triggered for the components in the bill of material without a planning run.

B. In multi-level backward scheduling, dependent requirements are calculated to the exact second.

C. In multi-level backward scheduling, dependent requirements are triggered at the start date for the planned order of the finished material.

D. If the individual material components are explicitly assigned to the operations of a routing, the requirement dates of the dependent requirements are scheduled at each start date of the operations.

Browse 80 Q&As
Questions 13

Which repetitive manufacturing options can you use to carry out line loading in the SAP ECC system and thus generate run schedule quantities (RSQ) from normal planned orders? (Choose three)

A. A suitable repetitive manufacturing profile that contains an option for automatic line selection

B. Manual assignment of planned production quantities in a planning table

C. Automatic selection of the production version by applying quota arrangement records in material requirements planning (MRP)

D. Automatic selection of the production version in material requirements planning (MRP) using selection methods setting

E. A planning algorithm from capacity planning

Browse 80 Q&As
Exam Code: C_TSCM42_65
Exam Name: SAP Certified Application Associate - Production - Planning & Manufacturing with SAP ERP 6.0 EHP5
Last Update: May 06, 2024
Questions: 80 Q&As

PDF

$49.99

VCE

$59.99

PDF + VCE

$67.99