Questions 4

Which should be done during the process Closing a Programme?

A. Confirm that key stakeholders are satisfied with the improvements

B. Provide an opportunity to plan a post-project review

C. Identify the need for future assessment of benefit realization

D. Enable all outstanding risks to be closed

Browse 112 Q&As
Questions 5

Which is a definition of a stakeholder?

A. Someone who represents a group of Business Change Managers, similar to a senior Business Change Manager

B. Role which provides the information hub and is the standards custodian for a programme and its delivery objectives

C. Any individual, group or organization that can affect, be affected by, or perceive itself to be affected by, a programme

D. Person with overall responsibility for ensuring that a project or programme meets its objectives and delivers the projected benefits

Browse 112 Q&As
Questions 6

What document provides terms of reference for the Sponsoring Group?

A. Programme Brief

B. Quality and Assurance Strategy

C. Resource Management Plan

D. Organization Structure

Browse 112 Q&As
Questions 7

Which statement refers to programme plans?

A. Describe the resourcing of programme activities

B. Present the rules for all parts of the organization

C. Describe why and how something will be undertaken in a programme

D. Define the organization's approach to achieving its corporate objectives

Browse 112 Q&As
Questions 8

What role initiates assurance reviews of supplier performance and ensures that lessons learned are implemented?

A. Senior Responsible Owner

B. Programme Manager

C. Business Change Manager

D. Programme Office

Browse 112 Q&As
Questions 9

Which is a responsibilityof the Programme Manager?

A. Approves programme's progression to next tranche

B. Defines risk thresholds for the programme's projects

C. Ensures appropriate programme assurance is in place

D. Reports regularly on programme progress

Browse 112 Q&As
Questions 10

What role, in approving the design of the programme, has a focus on compliance with corporate controls?

A. Programme Office

B. Programme Manager

C. Senior Responsible Owner

D. Business Change Manager

Browse 112 Q&As
Questions 11

Which label refers to one of the organizational risk perspectives?

A. Operational

B. Political

C. Portfolio

D. Economic

Browse 112 Q&As
Questions 12

Which is one of the three core concepts of the MSP framework?

A. Sponsoring Group

B. Vision

C. Principles

D. Risk management

Browse 112 Q&As
Questions 13

What programme role is MOST likely to also have a role within a project board to represent the interests of the business?

A. Programme Office

B. Programme Manager

C. Programme Board

D. Business Change Manager

Browse 112 Q&As
Exam Code: EX0-003
Exam Name: Managing Successful Programmes Foundation
Last Update:
Questions: 112 Q&As