Questions 4

The primary benefit of the Plan Schedule Management process is that it:

A. provides guidance to identify time or schedule challenges within the project.

B. tightly links processes to create a seamless project schedule.

C. guides how the project schedule will be managed throughout the project.

D. creates an overview of all activities broken down into manageable subsections.

Browse 920 Q&As
Questions 5

Sharing good practices introduced or implemented in similar projects in the organization and/or industry is an example of:

A. quality audits

B. process analysis

C. statistical sampling

D. benchmarking

Browse 920 Q&As
Questions 6

Project contracts generally fall into which of the following three broad categories?

A. Fixed-price, cost reimbursable, time and materials

B. Make-or-buy, margin analysis, fixed-price

C. Time and materials, fixed-price, margin analysis

D. Make-or-buy, lump-sum, cost-plus-incentive

Browse 920 Q&As
Questions 7

The processes required to establish the scope of the project, refine the objectives, and define the course of action required to attain the objectives that the project has been undertaken to achieve are grouped within which Process Group?

A. Initiating

B. Planning

C. Executing

D. Monitoring and Controlling

Browse 920 Q&As
Questions 8

Which statement correctly describes the value of a business case?

A. It provides the necessary information to determine if a project is worth the required investment.

B. It provides for alternative dispute resolution procedures in event of contract default.

C. It offers one of several alternative scenarios which assist in performing qualitative risk analysis.

D. It is used to help a project manager understand the scope of commercial advantages.

Browse 920 Q&As
Questions 9

The group technique that enhances brainstorming with a voting process used to rank the most useful ideas for prioritization is called the:

A. majority rule technique.

B. nominal group technique.

C. Delphi technique,

D. idea/mind mapping technique.

Browse 920 Q&As
Questions 10

Which of the following processes includes prioritizing risks for subsequent further analysis or action by assessing and combining their probability of occurrence and impact?

A. Qualitative risk analysis

B. Quantitative risk analysis

C. Risk management planning

D. Risk response planning

Browse 920 Q&As
Questions 11

Which schedule development tool and technique produces a theoretical early start date and late start date?

A. Critical path method

B. Variance analysis

C. Schedule compression D. Schedule comparison bar charts

Browse 920 Q&As
Questions 12

Design of experiments (DOE) should be used during which of the following processes?

A. Perform Quality Assurance

B. Total Quality Management

C. Perform Quality Control

D. Plan Quality

Browse 920 Q&As
Questions 13

Which of the following is an input to the Plan Risk Responses process?

A. Risk urgency assessment

B. Organizational process assets

C. Risk register

D. Schedule management plan

Browse 920 Q&As