Which is a purpose of a Product Description?

A. Provide the cost tolerance available for individual products

B. Define reporting frequency

C. Record the quality checks completed for the End Stage Report

D. Document the level of quality required of a product

Browse 296 Q&As
Questions 5

Which describes the 'Identify Risks' step within the recommended risk management procedure?

A. Identify responses to risks documented in the Business Case

B. Gather information about the project environment and objectives

C. Identify the roles to be involved in risk management activities

D. Identify uncertainties that may impact on the delivery of the project objectives

Browse 296 Q&As
Questions 6

Which statement defines a risk?

A. A certain event occurring in the future that will have a negative impact on the project's objectives

B. An event that has already occurred that the Project Manager must deal with immediately

C. An uncertain event, or set of events that, should it or they occur, will have an effect on the achievement of objectives

D. An uncertain event, or set of events that, should it or they occur, will be automatically escalated to the Project Board for a response

Browse 296 Q&As
Questions 7

In what product should the quality criteria for a specialist product be recorded?

A. Quality Management Strategy

B. Quality Register

C. Product Description

D. Project Product Description

Browse 296 Q&As
Questions 8

When considering how long the project stages should be, which might be a reason for one stage to be longer than others?

A. A substantial amount of the project budget is to be spent

B. More human resources are required than in other stages

C. The risk is lower

D. No changes to the project management team are envisaged

Browse 296 Q&As
Questions 9

Which is a valid statement about the Project Support role?

A. Can be performed by the Project Manager

B. Is an optional role for a PRINCE2 project

C. Produces Checkpoint Reports for the Project Manager

D. Can be combined with the Project Assurance role

Browse 296 Q&As
Questions 10

Which risk response type is a recommended response to both an opportunity and a threat?

A. Avoid

B. Reduce

C. Share

D. Reject

Browse 296 Q&As
Questions 11

Which should be provided by corporate or programme management before the Starting up a Project process commences?

A. A Project Brief

B. Sufficient information to identify the prospective Executive

C. The Project Initiation Documentation

D. Authority to initiate a project

Browse 296 Q&As
Questions 12

Which is a true statement about PRINCE2 event-driven controls

A. Event-driven controls take place at predefined periodic intervals

B. Event-driven controls are produced at the frequency defined in a Work Package

C. Event-driven controls are used for decision making

D. Checkpoint Reports are event-driven controls

Browse 296 Q&As
Questions 13

Which is a purpose of a Lessons Log?

A. Note any lessons that are raised in Checkpoint Reports

B. Record that corrective action is being taken

C. Escalate lessons to the Project Board

D. Raise improvements with Project Assurance

Browse 296 Q&As
Exam Code: PR2F
Exam Name: PRINCE2 Foundation Exam
Last Update: Apr 25, 2024
Questions: 296 Q&As

PDF

$49.99

VCE

$59.99

PDF + VCE

$67.99