How many tasks does the product-based planning technique describe?
A. One
B. Two
C. Three
D. Four
Which is the purpose of the Change theme?
A. Prevent change to baselined products
B. Identify, assess and control any potential and approved changes to baselined products
C. Establish mechanisms to monitor and compare actual achievements against those planned
D. Assess and control uncertainty
Identify the missing words in the following sentence, The six aspects of project performance to be managed are [?] costs, timescales and scope,
A. benefits, progress, risk,
B. benefits, quality, risk,
C. change, quality, progress,
D. benefits, customers, quality,
Which is a purpose of the Controlling a Stage process?
A. Produce a Team Plan for the work to be assigned to a Team Manager
B. Select and implement actions that will resolve deviations from a plan within tolerance
C. Obtain approvals for products delivered in a Work Package
D. Update a Project Plan to incorporate the actuals from a Stage Plan
Which is an objective of the quality review technique?
A. To baseline a product
B. To provide a common understanding of what products a project will create
C. To define the quality methods required within a project
D. To determine the quality responsibilities of a project team
In what product should the quality criteria for a specialist product be recorded?
A. Quality Management Strategy
B. Quality Register
C. Product Description
D. Project Product Description
Identify the missing words in the following sentence.
A problem/concern, a request for change and [ ? ] are the three types of issue.
A. a constraint
B. a deviation from tolerance
C. an off-specification
D. a threat
Which is a purpose of the Directing a Project process?
A. Provide the information required to confirm if it is worthwhile to initiate a project
B. Enable overall control of a project to be exercised by the Project Board
C. Establish the level of control required by the Project Board after initiation
D. Provide sufficient information so that the current stage can be reviewed and the next Stage Plan approved
Identify the missing product in the following sentence.
When assessing an issue during the Controlling a Stage process, the [ ? ] provides essential information to evaluate the viability of the project.
A. Project Brief
B. Benefits Review Plan
C. Project Initiation Documentation
D. Configuration Management Strategy
What do customer's quality expectations identify?
A. Standards that must be used in order to meet the level of quality needed
B. Skills required to develop the project product
C. Measurable definitions of the attributes required for a set of products to be acceptable to the customer
D. Reviewer names for each product