A software development program will launch iterative versions of new software called Alpha over two years Following that, a program will be released to the program team and developers to create new software called Beta While the program manager prepares the program closure plan tor Alpha, the program sponsor expresses concern about its support after program closure.
What should the program manager do as part of Alpha's program closure plan?
A. Execute the transition plan and Include Knowledge transfer to transition Alpha support to operations
B. Keep the Alpha program open until support is no longer required, then execute program closure
C. Adjust Alpha's exit criteria to ensure its support is included in the Beta program
D. Document the program closure procedure to ensure that resources are released from Alpha to develop Beta
A country is in the process of strengthening its defense program. A key project is not meeting its specified performance objectives. The project manager initiates a change request to address this issue.
What should the program manager do NEXT?
A. Consider the option to close out the key project
B. Evaluate the program and re-baseline the objectives
C. Assess the benefits and impact to the program.
D. Amend the risk register with the key project changes
The program manager plans to address a negative cost variance generating a red flag in the program management status report. What should the program manager do?
A. Contact the project sponsors to present the details, impacts, and possible corrective actions regarding the negative cost variance
B. Gather all the details, analyze impacts, determine corrective actions and present the findings to the governance board for direction
C. Work with program sponsor to compile impact analysis data to obtain additional funding for the program
D. Ask the program team to compile all details, analyze impacts, determine corrective actions and present to the governance board for direction
A program stakeholder is concerned about information they receive about a project. Who is responsible for reviewing the communications management plan to assure adequate information is provided to the stakeholder'?
A. Program sponsor
B. Communications manager
C. Project manager
D. Program manager
What is the MINIMUM fire rating for telecommunications spaces walls and wall linings, if not specified otherwise by local Authority Having Jurisdiction (AHJ)?
A. One hour
B. Two hours
C. Three hours
D. No minimum requirement
For design purposes, which of the following would be the typical size range of a 4-pair 100 ohm UTP or ScTP (FTP) cable?
A. .50 in to .75 in
B. .14 in to .25 in
C. .31 in to .43 in
D. .11 in to .18 in
A "sag" is a decrease in normal root mean square (rms) voltage or current lasting 0.5 cycles up to one minute.
A. False
B. True
Freestanding and cornerlock access floors consist of panels that are supported solely by pedestals.
A. False
B. True
What is the minimum clear working space between equipment and cross-connect fields in a TR?
A. 4 ft.
B. 2 ft.
C. 5 ft.
D. 3 ft.
For design purposes, which of the following would be the typical size range of a 4-pair 100 ohm UTP or ScTP (FTP) cable?
A. .50 in to .75 in
B. .14 in to .25 in
C. .31 in to .43 in
D. .11 in to .18 in