The development manager is managing the review of the responses received from bidders, and has asked the in-house test manager to provide a review checklist for the test management aspects of the responses.

Which of the following checkpoints would be appropriate?

A. The bidder's test policy should enforce that incident management fully conforms to IEEE 1044.

B. The bidder's project strategy shows that the data content of all the test environments conforms to EU standards.

C. The bidder's test plan shows that the application will be delivered for acceptance in six months time.

D. The bidder's project test plan depicts a phased implementation with later delivery dates to be confirmed and states that test deliverables will be developed using IEEE 829 as a guide.

Browse 65 Q&As
Questions 5

Which of the following product risks would be most effectively addressed just by static testing?

A. In the delivered application, one of the countries, as specified in the requirements, has not been correctly implemented.

B. The application takes too long to process a request for additional cover.

C. The test cases do not cover the key requirements.

D. The successful bidder may not deliver all the required functionality on time.

Browse 65 Q&As
Questions 6

Within the projects, a master test plan and phase test plan will be used. Following is a list of characteristics applicable for test plans:

Which THREE mentioned characteristics relate to the master test plan?

A. Any deviation from the procedures described in the test strategy document

B. The overall estimated costs, timescales and resource requirements

C. A detailed schedule of testing activities

D. The development deliverables to be tested

E. Which test staff members (names) will be involved and when

F. Level of requirements coverage achieved

Browse 65 Q&As
Questions 7

In addition to introducing the new team member, you have decided to raise motivation.

Which of the measures listed below would be the best measure to take in order to increase the motivation of the team?

A. Provide more time for testing in the schedule

B. Allow people to take some time off

C. Introduce entry criteria to the testing phase

D. Organize a meeting with senior management in which they address the importance of good testing for this project

Browse 65 Q&As
Questions 8

Which of the following is a benefit of independent testing?

A. Code cannot be released into production until independent testing is complete.

B. Testing is isolated from development.

C. Independent testers find different defects and are unbiased.

D. Developers do not have to take as much responsibility for quality.

Browse 65 Q&As
Questions 9

In addition to risk, identify TWO other components of a testing strategy.

A. The entry and exit criteria for each test phase

B. Test training needs for the project resources

C. The test design techniques to be used

D. Test performance indicators

E. The test schedule

Browse 65 Q&As
Questions 10

Which of the following is a project risk mitigation step you might take as test manager?

A. Testing for performance problems

B. Hiring a contractor after a test analyst leaves the company

C. Arranging a back-up test environment in case the existing one fails during testing

D. Performing a project retrospective meeting using the test results after each increment

Browse 65 Q&As
Questions 11

Which test management control option is most appropriate to adopt under these circumstances?

A. Introduce mandatory evening and weekend working to retrieve the 3 week slippage.

B. Reconsider the exit criteria and review the test plan in the context of the current situation.

C. Advise the user community regarding the reduced scope of requirements and the additional incremental delivery.

D. Arrange a meeting with the user community representatives to discuss the user interface.

Browse 65 Q&As
Questions 12

The introduction of reviews and inspections has often failed as a process improvement action.

Identify the THREE most important measures that should be taken to reduce the risk that this test process improvement will fail.

A. Process ownership and experienced moderators who drive the inspection process.

B. Management support

C. Training of those involved

D. The availability of stands and processes

E. Usage of a more traditional software development lifecycle

F. Alignment with software process improvement

G. Using a reference model, e.g. TMMi

Browse 65 Q&As
Questions 13

A test log is one of the documents that need to be produced in this domain in order to provide evidence of testing. However, the level of detail of test logs can vary. Which of the following is NOT an influencing factor for the level of detail of the test logs being produced?

A. Level of test execution automation

B. Test level

C. Regulatory requirements

D. Experience level of testers

Browse 65 Q&As
Exam Code: CTAL-TM
Exam Name: Certified Tester Advanced Level - Test Manager (CTAL-TM)
Last Update: May 04, 2024
Questions: 65 Q&As

PDF

$49.99

VCE

$59.99

PDF + VCE

$67.99