Identify the missing words in the following sentence... A PRINCE2 project is and controlled on a stage-by- stage basis?
A. Planned, monitored
B. Developed, reported
C. Designed, assigned
D. Planned, produced
Identify the missing word(s) in the following sentence... The [?] is used by the Project Manager to capture and maintain information on all of the identified threats and opportunities relating to the project.
A. Risk Register
B. Risk Management Strategy
C. Issue Register
D. Risk owner
As part of the ‘closing a project’ process, the project manager needs to assess whether the outcomes are likely to deliver the expected performance improvements post-project.
In which step of 'business case management' technique should the project manager assess this?
A. Develop
B. Check
C. Maintain
D. Confirm
Which statement about the role of the project manager is CORRECT?
A. The project manager must not delegate any responsibilities
B. The project manager must not take on an additional role
C. The project manager role must not be shared
D. The project manager must not come from the supplier
Which describes a purpose of the ‘organization’ theme?
A. To direct and control an organization with regard to quality
B. To facilitate communication by defining who will deliver the products
C. To establish accountabilities across all the project levels
D. To establish mechanisms to control unacceptable deviations
Which management product is the team manager role responsible for producing?
A. Stage plan
B. Checkpoint report
C. Project product descriptions
D. Highlight report
Which is a purpose of the 'managing a stage boundary' process?
A. To enable the project board to approve the continuation of the project
B. To exercise overall control over the project while delegating day-to-day management
C. To assign work to be controlled by the team manager
D. To define the work that needs to be done to deliver the project product
Which is a purpose of a Project Brief?
A. Enable the assembly of the project mandate
B. Describe the reporting requirements of the various layers of management involved with the project
C. Describe how changes to products will be controlled
D. Provide a solid basis for the initiation of the project
Which of the following does PRINCE2 say are typical characteristics of a Project Board member?
A. Democratic, supportive, can make decisions
B. Hard working, experienced, forceful
C. Focused, steadfast, autocratic
D. Have authority, credibility, ability to delegate, available when required
What is defined within the Organization theme?
A. Project resource requirements
B. Project acceptance criteria
C. Responsibilities for managing teams
D. Jobs for individuals to perform