Questions 4

Once the project's WBS has been created what process may happen next?

A. Estimate activity resources

B. Define activities

C. Estimate activity durations

D. Sequence activities

Browse 323 Q&As
Questions 5

John works as the project manager for Honeywell Inc. He is involved in the periodic collection and analysis of baseline versus actual data to understand and communicate the project progress. Which of the following techniques is used in generating performance reports?

A. Work performance information

B. Change requests

C. Work performance measurements

D. Forecasting method

Browse 323 Q&As
Questions 6

Harry works as the project manager for his organization. He is creating the activity list and would like to tag those activities that are comprised of apportioned effort. Which of the following is the best example of apportioned effort?

A. Adding features to the project's product that is not included in the project scope.

B. Managing the day-to-day events of a project.

C. Creating software as defined in the project scope.

D. Completing project activities as start-to-start events.

Browse 323 Q&As
Questions 7

Fred is the project manager of the NHA project. This project has a BAC of $2,456,900 and is sixty percent complete. Fred has crashed the project, which has driven the project costs to date to $1,525,140, but his project is five percent more complete than what was planned. What is the schedule variance for this project that Fred needs to report to the management?

A. $176,675

B. $122,845

C. -$85,000

D. -$51,000

Browse 323 Q&As
Questions 8

You are the project manager for your organization. Your project will need four electrical engineers for the project though there are no electrical engineers within your department. This scenario is best described as which one of the following terms?

A. Assumption

B. Risk

C. Resource requirement

D. Resource constraint

Browse 323 Q&As
Questions 9

You are the project manager for your organization. You are working with your project team to define the project network diagram. Several of the activities in the project schedule appear to have external constraints. Who among the following determines which dependencies are external to the project?

A. Project team

B. Project sponsor

C. Project manager

D. Project management team

Browse 323 Q&As
Questions 10

Which of the following processes fall under the Project Integration Management knowledge area? Each correct answer represents a complete solution. Choose all that apply.

A. Quality Assurance

B. Project Plan Development

C. Integrated Change Control

D. Project Plan Execution

Browse 323 Q&As
Questions 11

Joe is the project manager of the HJN Project. Joe's project is a renovation of an office building. There must be 30 hours between the painting activity and the carpet activity in the project schedule to eliminate the risk of wet paint getting on the carpet. What is the best approach Joe can do to alleviate this issue?

A. Add lead time to the painting activity.

B. Change the relationship of the carpet activity and the painting activity to finish-to-finish.

C. Create a dummy activity between the painting activity and the carpet activity for the duration of the drying process.

D. Add lag time to the carpet activity.

Browse 323 Q&As
Questions 12

You are the project manager of the NHQ Project. You are coaching Alice, a new project manager, on the relationships in a project network diagram. Which relationship type between activities are the most common?

A. SS

B. FS

C. FF

D. SF

Browse 323 Q&As
Questions 13

You are the project manager of the GHQ Project. You are working with your project team to create the project network diagram. You have created the PND and are identifying the critical path with your team using your project management information system. All of the activities on the critical path are showing in red in the software that you are using to evaluate the critical path. What are schedule activities on the critical path called?

A. Critical activities

B. Action items

C. High alert activities

D. Red rated activities

Browse 323 Q&As