Which of the following is important to include in the acceptance procedure?
A. Definition of detailed scope of works, subcontractor pricing elements and unambiguous definition of acceptance criteria and related documentation and other evidence.
B. Clear procedure of how and in what timeline acceptance is required to be given, related triggers, unambiguous definition of acceptance criteria and related documentation and other evidence.
C. Definition of detailed scope of works, customer invoicing and pricing elements, unambiguous definition of acceptance criteria and related documentation and other evidence.
D. Clear procedure of how and in what timeline acceptance is required to be given, related triggers, risk management plan, and back-to-back customer and vendor contracts.